Daniel Atkinson Limited Alternative Dispute Resolution
Email:daniel@atkinson-law.com 7 Oakland Drive, Robertsbridge, East Sussex TN32 5EX England
Mobile: 07778 347 777 Tel: +44 (0) 1580 880 532 Fax: +44 (0) 1580 881 140

 

Adjudication
Fleming Builders Limited v Mrs Forrest [2008] CSOH 103

© Daniel Atkinson 23 October 2008


KEYWORDS: Fleming Builders Limited v Mrs Forrest [2008] CSOH 103, Costain Ltd v Strathclyde Builders Ltd [2004] SLT 102, Diamond v PJW Enterprises Ltd [2004] SC 430, Domsalla v Dyason [2007] EWHC 1174, Rupert Morgan Building Services (LLC) v David Jervis [2004] BLR 18, John Stirling v Westminster Properties Scotland Ltd [2007] BLR 537, SBCC Building Contract with Contractors Design Portion, Clause 30.1.1.1, Clause 30.1.1.4, Clause 30.1.1.5, Clause 41A.6.5, contract, contracting parties, agent, individual, company, adjudication, contractual adjudication, retention, set-off, withholding notice, evidence, exclusion, natural justice, jurisdiction, Lord Menzies.

In Fleming Builders Limited v Mrs Forrest [2008] CSOH 103 the main issue was whether the adjudicator had jurisdiction which depended on whether there was a contract and if so whether the contract for work on the residential property was made with the occupier Mrs Forrest or with a company KWF Holmes Ltd.  Lord Menzies was also required to decide whether the adjudicator had acted in breach of natural justice. Although the judgment deals at length with the evidence, the judgment is simply the application of well established adjudication principles to the facts.


The Issue of the Contract

In the adjudication between Fleming and Mrs Forrest, the adjudicator decided that there was a contract and that it was between the parties to the adjudication and that she had jurisdiction. She then proceeded to order Mrs Forrest to make payment of £112,598.75 plus interest to Fleming.

Lord Menzies held that there was no contract between Fleming and KWF and distinguished  John Stirling v Westminster Properties Scotland Ltd [2007] BLR 537. He recognised that there might be cases in which loosely worded correspondence sent after the formation of a contract, for example in the name of a company rather than in the name of the individual who was the true contracting party, may be construed liberally so that the company was acting as an ad hoc agent for the individual contracting party. Lord Menzies found that was not the situation in the instant case. There is no evidence pointing to the formation of a contract between Fleming and KWF. He decided that the fact that payments for works performed under the contract were made from an account in KWF's name was neither here nor there.

Lord Menzies decided that there was indeed a contract between Fleming and Mrs Forrest and placed emphasis on the conduct of the professional team and the various documents produced consistent with there being a contract and the experience of Mrs Forrest in other developments.

Lord Menzies held that the adjudicator had jurisdiction.


Natural Justice

Mrs Forrest argued that that the adjudicator failed to address its argument that there was no contract between the parties, but Lord Menzies rejected this on its facts referring to Diamond v PJW Enterprises Ltd [2004] SC 430.

The interesting point is that Lord Menzies appears to have treated the adjudicator's determination of this issue as within her jurisdiction. the judgment shows that there were substantive submissions to the adjudicator on her jurisdiction, but there is no statement that Mrs Forrest continuously objected to jurisdiction.

It appears to have been accepted that the adjudicator's decision was within her jurisdiction as it was argued that a statutory adjudication (ie one which fell within the provisions of the Housing Grants Construction and Regeneration Act 1996) was to be distinguished from a purely contractual adjudication. It was argued that the adjudication fell into the latter category, and that purely contractual adjudications must be regarded as a species of arbitration so that the well-established principles on which the Court may interfere with an arbiter's decision applied equally to the instant case.

Lord Menzies rejected that approach as an artificial and misconceived distinction.

Lord Menzies considered there was no justification for a distinction between the way in which the Court would approach the decision of an adjudicator who had dealt with a dispute under the Act and the Scheme, and the way in which the Court would deal with an adjudicator who had dealt with a dispute under the contract. He considered that the observations of the Lord Justice Clerk in Diamond at paragraph [20] were general and not confined to adjudications within the context of the Act and the Scheme, although in that case the adjudication was under the Act and the Scheme for Construction Contracts (Scotland) Regulations 1998..

Lord Menzies held that the adjudication in the instant case was a form of provisional resolution only and it did not oust the jurisdiction of the courts or of an arbiter. Its primary purpose was to regulate the dispute, pending a definitive resolution of it by litigation, arbitration or agreement. Particularly when read with Lord Macfadyen's Opinion in Diamond, it was clear that the position of an adjudicator was quite distinct from that of an arbiter. There was no reason, in principle or in practice, why the Court faced with the decision of an adjudicator appointed under the relevant clauses of the instant standard form of contract should treat it as an arbitration rather than an adjudication, nor why it should treat the decision any differently from one made in the context of section 104 of the 1996 Act and the 1998 Scheme.


Retention and Set-Off

The adjudicator found that a letter was not a valid Withholding Notice in terms of clause 30.1.1.4 of the contract, because it was in the name of KWF and accordingly not from the employer Mrs Forrest. Lord Menzies agreed with the analysis, but held in any event that  even if the adjudicator was wrong on this point, any error was intra vires and accordingly not subject to challenge in the instant proceedings.

It was argued that unless the contract specifically excludes the right at common law of retention and set-off then Mrs Forrest was entitled to retain and set-off sums due to them against any decision of the adjudicator. It was argued that their right to retain and set-off at common law was not excluded by the contract.

Lord Menzies disagreed and referred to Clauses 30.1.1 to 30.1.15 which he decided provided a scheme whereby the contract excluded the right to common law retention or set-off. The only means by which an employer could properly refrain from making payment of a sum due under an architect's certificate was by the contractual mechanism contained in that scheme. He held that it would defeat the whole purpose of the contractual scheme if common law retention or set-off was available in any event. It would also defeat the purpose of adjudication to provide a swift but provisional regulation of a dispute ad interim if it were open to a party to seek to retain or set-off sums against a decision of an adjudicator. He observed that his reasoning was consistent with that in Rupert Morgan Building Services (LLC) v David Jervis [2004] BLR 18.


Exclusion of Evidence

It was submitted that it would have been reasonable for the adjudicator to conduct a conference call with a key witness on his return from holiday. It was aid that he had expressed willingness to participate in a conference call. It was argued that a failure to do so was a breach of natural justice.

Lord Menzies found that there was no evidence from the witness when he was on holiday, that he was asked and whether he was willing to attend a conference call. It was held that in light of the lack of evidence from the witness and in the absence of any argument that the adjudicator acted outwith the wide powers and discretion conferred on her in terms of the contract, there was no force in the attack on the adjudicator based on a possibility of a breach of natural justice. The adjudicator had the affidavit of the key witness, the benefit of having heard evidence from witnesses for both sides and full legal submissions together with a substantial body of documentary evidence and in the short timetable the adjudicator could not be criticised for proceeding to reach her decision without such a conference call.


Conclusion

Lord Menzies held that the adjudicator had jurisdiction, there was nothing to suggest that her decision was contrary to the rules of natural justice and there were no grounds on which Mrs Forrest could seek to retain or set-off sums against the adjudicator's decision.